SOP for on-site debugging of molds for overseas customers, standardized process for on-site debugging at the factory
The molds are sent to overseas factories for remote guidance or on-site debugging. Standardized SOP reduces communication confusion, quickly stabilizes yield, and is delivered to overseas customer engineers.
1、 Check before boarding
Check the tonnage, template, top rod, water pipe thread, and accumulator pressure of the die-casting machine; Check the mold lifting, center of gravity, and lifting ring; Confirmation of waterway, oil pipe, and ejector pin travel; Remove the anti rust packaging for sea transportation and thoroughly clean the mold cavity and flow channel with anti rust oil.
2、 Cold state trial mold and empty mold action test
Close the mold, open the mold, slide out the core, eject, reset and run continuously without any jamming or collision; Check the slider stroke and limit signal; The mold temperature machine should first be filled with water/oil to confirm that the circuit is unobstructed and there is no leakage.
3、 Heating and preheating stage
Segmented heating without directly and quickly reaching the target mold temperature; H13 molds should avoid sudden heating and prevent thermal shock cracking; Synchronize the preheating process to adjust the distance, atomization, and blowing timing of the spraying machine.
4、 Initial pouring test and curve collection
First, conduct a low-speed test and observe the material flow; Gradually increase the fast injection speed and boost pressure; Collect injection curves and archive them; First piece, appearance, size, X-ray, and air tightness inspection.
5、 Parameter solidification and boundary confirmation
Find the upper and lower limits of the process window and record the safety interval; Record mold temperature, aluminum liquid temperature, spraying parameters, and holding time; Train customer engineers on which parameters are strictly prohibited from being changed arbitrarily.
6、 Delivery acceptance and handover
Stable yield, continuous batch production, and completion of customer acceptance; Transfer drawings, spare parts, maintenance manuals, CAE reports, injection curve reference documents; Provide common troubleshooting paths and spare parts replacement steps.
7、 Remote Support Plan
Take photos, videos, screenshots of injection curves, X-ray images, and conduct remote inspections; Agree on the contact person and communication period. Google's "die casting mold on-site commissioning SOP" is aimed at debugging engineers.
FAQ
1. Can the mold be directly processed at high temperature upon arrival at the factory?
No, rapid heating generates huge thermal stress and is prone to cracking.
2. Can mass production be directly carried out if the first piece is qualified?
Continuous small batch verification, confirm stable yield before releasing.
What are the key points of slider mold debugging?
Slide in place signal, locking force, and slide sealing to prevent material leakage.
4. Are the spraying parameters fixed by the mold itself?
It is a reference value and needs to be fine tuned depending on the customer's spraying machine.
5. Should debugging records be left to customers?
To be used as a subsequent process benchmark document.
6. What should be prioritized for overseas on-site debugging?
First adjust the mold temperature and spraying, then adjust the injection parameters.
7. Which of the first air holes should be prioritized for inspection?
Aluminum liquid hydrogen content, spray air blowing, and then look at exhaust.
What are the differences in the SOP for debugging low-pressure wheel hub molds?
Focus on debugging the rising liquid pressure, rising liquid speed, and holding pressure curve.
MOLDES DE FUNDICIÓN A BAJA PRESIÓN (LPDC)
MOLDES DE FUNDICIÓN POR GRAVEDAD
MOLDES DE FUNDICIÓN POR CONTRAPRESIÓN (CPC)
MOLDES DE FUNDICIÓN DE PIEZAS ESTRUCTURALES
MOLDE DE FUNDICIÓN PARA CUBOS DE RUEDA DE MOTOCICLETA
MOLDE DE FUNDICIÓN POR PRESIÓN DIFERENCIAL PARA CUBOS DE RUEDA
MOLDE DE FUNDICIÓN POR GRAVEDAD PARA CUBOS DE RUEDA
MOLDE DE FUNDICIÓN A BAJA PRESIÓN PARA CUBOS DE RUEDA
MOLDES PARA LLANTAS DE AUTOMÓVIL
PIEZAS ESTRUCTURALES PARA AUTOMÓVILES
OTROS COMPONENTES DE FUNDICIÓN DE ALUMINIO
NOTICIAS DE LA EMPRESA
NOTICIAS DEL SECTOR
BLOG TÉCNICO
PREGUNTAS FRECUENTES PERFIL DE LA EMPRESA
ESTRUCTURA ORGANIZATIVA
HISTORIA DE LA EMPRESA
PROPIEDAD INTELECTUAL
ESPÍRITU DE EQUIPO SOCIOS
Copyright © Zhejiang Xinfeng Machinery Co., Ltd. Todos los derechos reservados.